User Request to Copy POV(s)

You can copy data from one point of view to another. For example, if you wanted to create a "what if" version of a point of view, you could start with data that was already included in an existing point of view, copy it to a new point of view, and then do some additional edits and calculations.

You can copy more than one point of view at time. For example, you could copy 12 periods of data from the calculation cube (PCM_CLC) to the reporting cube (PCM_REP), and you could copy 6 periods of data from Actual to Forecast in the same cube. You can also use substitution variables for POV members. See Using Substitution Variables in User Requests.

The following are some examples of users requests to copy a POV.

User Request to Copy a POV Using a Job

Copy Pov Using Job 'Copy Input Job 1'

User Requests to Copy a POV Identifying Specific Options

copy input data from pov FY24:Jan:Actual:Working to FY24:Feb:Actual:Working
copy all the data from FY24:Jan:Actual:Working to a new pov FY24::Feb::Actual::Working save job as 'Clear Input for FY24 Jan POV'

User Requests to Copy Multiple POVs

Copy All Data for ALL FY24 povs to FY25
copy pov range "Feb" through "Dec" to Scenario Plan
copy fixed pov Jan:Actual:Working pov range FY24 input data to FY25
Copy input Data for ALL FY24:Working povs to Final
copy all data from pov FY24::Jan::Actual::Working source cube PCM_CLC to pov FY24::Feb::Actual::Working destination cube PCM_REP
Copy input Data for ALL FY24:Jan povs to &currMonth

User Requests Replacing POV Members with Substitution Variables

Copy pov source pov '&CurrYear::&SourceMonth::Actual::Working' destination pov '&DestYear::&DestMonth::Actual::Working' pov delimiter '::' copy type 'INPUT' create destination pov 'true' source cube 'PCM_CLC' destination cube 'PCM_REP'
Copy POVs fixed pov Actual:Working &PriorYear:Jan to &CurrYear:&CurrMonth copy allocated values
Copy POVs fixed pov &CurrScenario:&CurrVersion FY24:Jan to FY24:Aug copy all values