Cancel a Segmentable Activity

You can cancel any pending segmentable activity or pending segment of a segmentable activity.

In addition to the fields usually present on the Cancel activity page for single-day activities, this page has a special segmentable activity is finished check box that allows you to cancel the entire segmentable activity together with the current segment. Checking the check box, confirms that you are completing the entire activity, together with the segment.

If you choose to cancel only the current segment (by leaving the check box unchecked), the Cancel activity page has the Time to complete field showing the remaining duration of the segmentable activity. Initially, the Time to complete value is the total duration of the segmentable activity minus the duration of the finished segments. The Time to complete can be adjusted simultaneously with canceling a segment. If you cancel the segment before the completion of the time to complete, the remaining duration is moved either to the non-scheduled pool or to a new segment on the next day, depending on where the activity was created and the activity is marked as canceled.

If you choose to cancel the entire segmentable activity and check the check box, the Time to complete field is hidden.