Change Activities in Groups

You can make changes to multiple activities at once.

Before you start

The Group Change option must be enabled for your user type.

Here's what to do

  1. Click the hamburger icon and then click Dispatch Console.
  2. Open the List view.
  3. Select a resource or bucket from the resource tree.
  4. Select the items that you would like to change.
  5. Click Change from the top of the Work Area.
    The Change group of activities dialog displays a list of parameters that you can edit.
  6. When you have confirmed your changes, click OK.