You can link a segmentable activity with another segmentable activity, using specific
link types such as Simultaneous, Finish to Start, and Start to Start. You can also see the
activity details that show the graphical representation of the linked
activities.
-
Ensure that you have created the segmentable activities that you want to
link.
-
Open the Activity details page for the segmentable
activity for which you want to add a link.
-
Go to the Activity link tab and click Add
link.
-
Select the type of link you want to add. For example, Start after.
-
Search for the other segmentable activity that you want to link the current
activity with.
-
Click Link.
The activities are linked and the links show on a GANTT-like chart. If
you try to add an unsupported activity link type and/or constraint, a warning is
displayed and no link is added.
-
If you want to unlink the activities, click
Unlink.