How do I use segmentable activities for multi-day tasks?
Segmentable activities are activities that you can carry over to the next day. They're normal activities that are split into segments and managed individually. A Segmentable activity contains a set of activities, each representing a single-day task with definite start and end times.
You create a segmentable activity based on the total duration of
the activity, number of segments, and the duration for each segment.
You must also identify the route or the sequence of the segments in
the activity. You can represent segmentable activities graphically
and assigned them to one or multiple resources. Segmentable activities
have these characteristics:
These activities also respond to events that occur as the activity progresses.
Mobile workers receive segments of segmentable activities in their routes and can handle them as regular single-day activities.
Segmentable activities are represented as separate bars on the Time view, can be assigned to buckets or mobile workers, and support time monitoring and status changes.
-
Segmentable activities can be linked with regular activities.
- Segments can be generated and planned for up to 99 days in the future.