Carry Forward Purchase Order Report Summary

The summary tab shows these items:

  • Number of purchase orders that are final closed and reopened for the carry forward
  • Control budget amounts by period
  • Budget import summary
    • The budget import status will indicate cases where the budget wasn’t imported.

Suggested Actions On Budget Not Imported

PO Charge Account Filter Fund Values Status Description Actions

Not Attempted

The budget import wasn’t attempted.

Reasons: There is more than one control budget with the same source budget, project control budget

Manually enter the budget amounts by control budget using the Enter Budgets in Spreadsheet task.

Failure

There was a budgetary control validation error during the budget import.

Failures: budget period isn’t open, budget adjustments aren’t allowed

After correcting the validation error manually import the budget amounts Manually enter the budget amounts by control budget using the Enter Budgets in Spreadsheet task. Or by source budget using the budget interface.

  • Purchase orders not carried forward
  • If a purchase order can’t be carried forward, these errors are displayed.
Error Message Description Actions

The purchase order can't be finally closed because it didn't pass budgetary control validations.

There was a budgetary control validation error during the final close of the purchase order. The message details include the error.

Failures: control budget status isn’t in use, budget period isn’t open.

After correcting validation error, rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

The project burden of the purchase order can't be finally closed because it didn't pass budgetary control validations.

There was a budgetary control validation error for the project burden during the final close of the purchase order. The message details include the error.

After correcting validation error, rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

The purchase order can't be reopened because it didn't pass budgetary control validations.

There was a budgetary control validation error during the reopen of the purchase order. The message details include the error.

Failures: control budget status isn’t in use, budget period isn’t open

After correcting validation error,

rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

The project burden of the purchase order can't be reopened because it didn't pass budgetary control validations. There was a budgetary control validation error for the project burden during the reopen of the purchase order. The message details include the error.

After correcting validation error,

rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

There is no budgetary control activity to carry forward. There was no budgetary control activity during final close of the purchase order

No action required or

Manually final close and then reopen the purchase order with the new budget date if you want to reserve funds for this purchase order in the new budget year.

The reopen sub process failed because it can’t find a control budget to reserve funds. The final close sub process is returned/reset to previous values..

There was no budgetary control activity during the reopen of the purchase order

Typical reasons: Period range of the control budget the balance is being carried

forward to hasn’t been extended, control budget hasn’t been created or. Control level is set to None.

Update the control budget and rerun the Carry Forward Purchase Order Budgetary Control Balances.

or

When the control level is set to none correctly, manually final close and then reopen the purchase order with the new budget date if you want the budget date to be updated to the new budget year.

A purchase order carry forward activity exists for the summary budget but not for the source budget. The budget won't be updated for the summary budget. The purchase order impacted the summary control budget but not the detail control budget as the detail control budget is set with control level as none. The budget can’t be created as for the summary control budget since it comes from the detail control budget.

Update the control budget settings so that the detail and summary control budget are consistent.

After correcting the setup,

rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

A purchase order carry forward activity exists for the source budget but not for the summary budget. The budget should not be updated for the summary budget. The purchase order impacted the detail control budget, but didn’t impact the summary control budget and therefore isn’t created as the budget balances will be out of sync.

Update the control budget settings so that the detail and summary control budget are consistent.

After correcting the setup,

rerun the Carry Forward Purchase Order Budgetary Control Balances

or

Manually final close and then reopen the purchase order with the new budget date.

The schedule cannot be finally closed because the distribution budget date is after the carry-forward cutoff date. The budget date of one of the distributions is after the budget date selected for the final close

No action required

or

If some of the distributions are before the budget date, manually final close and then reopen purchase order with the new budget date.

The purchase order can't be finally closed because the PO charge account doesn't match the account selection criteria that's specified for this process. The PO charge account of one of the distributions doesn’t match the PO Charge Account Filter values selected.

Rerun the Carry Forward Purchase Order Budgetary Control Balances with the correct PO Charge Account Filter values

or

manually final close and then reopen the purchase order with the new budget date.