Pay Through Dates and Payment Dates in Payment Process Requests

Payment process requests use the Pay Through Date and Payment Date values to determine whether to select an installment for payment and take a discount.

The following scenario illustrates the effect of these values in a payment process request, along with the impact of the Always Take Discount option.

Pay Through Dates and Payment Dates in Payment Process Requests

An invoice that's ready for payment has an installment with the following information:

  • Due date of August 30, 2015

  • First discount date of July 15, 2015, for 150 USD

  • Second discount date of July 30, 2015, for 100 USD

The Date Basis on the payment process request is Pay Date, and the Pay Date Basis for the supplier site is set to Discount.

This table provides examples of different Pay Through Date, Payment Date, and Always Take Discount combinations, and the resulting installment and discount information.

Example

Pay Through Date

Payment Date

Always Take Discount Option

Installment Selected?

Discount Taken Amount

1

July 14, 2015

July 17, 2015

Enabled or disabled

No. The Pay Through Date is before the first discount date.

None. The installment isn't selected.

2

July 15, 2015

July 17, 2015

Enabled or disabled

Yes. The Pay Through Date is on or after the first discount date.

100 USD. The Payment Date is after the first discount date, but before the second discount date.

3

July 15, 2015

July 31, 2015

Disabled

Yes

None. The Payment Date is after the discount dates and the Always Take Discount option is disabled.

4

July 15, 2015

July 31, 2015

Enabled

Yes

150 USD. Although the Payment Date is after the discount dates, the first discount is taken because the Always Take Discount option is enabled.

5

July 15, 2015

August 31, 2015

Disabled

Yes

None. The Payment Date is after the due date and the Always Take Discount option is disabled.

Note: Interest may be calculated depending on your settings.

6

July 15, 2015

August 31, 2015

Enabled

Yes

150 USD. Although the Payment Date is after the due date, the first discount is taken because the Always Take Discount option is enabled.

Note: Interest may be calculated depending on your settings.
Note: Results are different if the Date Basis is Due Date, or the Date Basis is Pay Date and the supplier Pay Date Basis is Due. In this case, the payment process request selects the installment only when the Pay Through Date is on or after the due date.