Cancel or Make Changes to Scheduled Processes
Life is full of second chances! After a scheduled process is submitted, you can still cancel it or make other changes in the Scheduled Processes work area.
What you can do to the process depends on its status. Also, depending on what you've access to, you can even work on processes that someone else submitted. If you need to cancel processes that someone else submitted, ask your security administrator to assign you a custom role that has the ESS Administrator Role (ESSAdmin).
Make Changes to Processes
Select the scheduled process in the Search Results table. Here are some things you might be able to do.
Task | Prerequisite | Procedure |
---|---|---|
Edit Schedule Change the submission schedule, for example, to submit it biweekly instead of weekly. |
This option is there only if you select the row with the process ID you got when you submitted the process to run on a schedule. The row should be the parent node when you view the search results in a hierarchy, and the status should be Wait. | From the Actions menu, select Edit Schedule. |
Edit Output Change output options of a process, for example, from HTML format to PDF. |
You can do this only if the process generates output, and hasn’t started running yet. | From the Actions menu, select Edit Output. |
Put On Hold Pause the process. |
Click the Put On Hold button. | |
Release Process Resume a process that's on hold so that it continues to run. |
Click the Release Process button. | |
Change Process Priority Change the priority of a process to affect when it runs. When there are many submitted processes, those with a lower number, for example 2, would usually run before those with a higher number, for example 7. |
You can do this only if your implementor has enabled priorities for scheduled processes,and you've a custom role that has the ESS Administrator Role (ESSAdmin). You can change priorities only for processes that have the Blocked, Hold, Ready, or Wait status. |
Click the Change Process Priority button. |
Cancel a Process
Select the scheduled process in the Search Results table, and click Cancel Process.
Cancel a Process Running on a Schedule
- Find the original submission, the row with the process ID you got when you submitted the process. The row should be the parent node when you view the search results in a hierarchy, and the status should be Wait.
- Click Cancel Process.
When you cancel this original submission, you cancel any current and future runs based on the schedule you had set.
What to Do If Processes Take a Long Time to Cancel
Sometimes it takes a while for a process to finish canceling. So, you can use the Actions menu to end it. The option you get depends on the process.
Option | Description |
---|---|
Hard Cancel | To end the process shortly after you canceled it, without waiting for the cancellation to finish by itself. |
Force Cancel | To end a process that has been canceling for over 30 minutes but isn't done yet. |
Processes on Remote Servers
Option You Used to End Your Process | Field that Shows the Status of the Remote Process | Status of Process on Remote Server |
---|---|---|
Force Cancel | Remote Process Status |
|
Hard Cancel | External Job Status |
|
Cancel Processes in Bulk
You can cancel up to 100 processes at once, as long as the processes haven't reached a final state.
-
Click
. -
In the Search section, select Cancelable Processes from the Saved Search list.
-
Make sure that what you get in the Search Results table meets these requirements:
-
No more than 100 processes
-
Only processes with a cancelable status:
-
Wait
-
Ready
-
Running
-
Completed
-
Blocked
-
Hold
-
Paused
-
Pending Validation
-
Schedule Ended
-
Error Auto-Retry
-
-
-
Use the Search section to change your search results, if you need to.
-
Select Cancel Processes in Bulk from the Actions menu.