Plan Your Production Cutover

Plan your production cutover for Oracle Fusion Cloud Financials Embedded Banking Services with PNC by allowing sufficient notice for your planned go-live date and accounting for the bank's year-end freeze period.

  • Allow time for production cutover notice.

    Provide at least two weeks notice to PNC for the planned production cutover. If outsourced check printing is involved, additional time might be required. Share your planned go-live date with the bank early enough to meet the required notice period.

  • Schedule the go-live date outside PNC's freeze period.

    The bank observes a freeze period during late December and early January. If your planned go-live date falls during this period, work with the bank to identify a date outside the freeze period.