Why is the assistant saying the partner contribution start date hasn't been specified even after I enter Aug 6, 2026, as the start date?

The assistant requires dates in a supported date format. If the date is entered in a format the assistant doesn't recognize, it might treat the start date as missing.

Use one of these formats:

  • YYYY-MM-DD, for example: 2026-08-06
  • Full month format, for example: August 6, 2026

Avoid shortened or ambiguous date formats such as Aug 6,2026 or 08/06/2026.

Why is the assistant using only part of the amount I entered?

If you enter an amount with a comma, such as 25,500.00, the assistant might read only the digits before the comma. It might interpret the amount as 25 and treat 500.00 as another value or parameter.

To avoid this issue, enter amounts without commas. For example, use 25500.00 instead of 25,500.00.

If the request starts a scheduled process, check the process report to confirm that the amount and other parameters were interpreted correctly.

Why does the assistant show matching joint ventures when I enter a joint venture name?

Joint venture names are case-sensitive and must match the exact names in Joint Venture Management. If you enter a name with different capitalization, such as Jointventurename, the assistant won't treat it as an exact match.

When this happens, the assistant shows possible matches, such as JOINTVENTURENAME1, JOINTVENTURENAME2, or JOINTVENTURENAME 10, and asks you to provide a valid joint venture name.

Why did I get "No partner contribution shortfall was found" when I expected a shortfall for the specified stakeholder?

Check whether the stakeholder name is entered exactly as it appears in Joint Venture Management. Stakeholder names are case-sensitive and must match the exact names in Joint Venture Management. For example, if the stakeholder is STAKEHOLDER1 but you enter Stakeholder1, the assistant might not identify the correct stakeholder. It might not show matching stakeholder records, and it might return a normal-looking response saying no partner contribution shortfall was found.

Why doesn't the assistant use all the parameter values I specify for partner contribution scheduled processes?

The assistant uses only the values it asks you to provide for the task. If you include other scheduled process parameters in your prompt, the assistant doesn't use them and applies the default values for those parameters.

Example prompt:

Create a partner contribution for joint venture: JOINTVENTURENAME, stakeholder: STAKEHOLDERNAME, start date: 2026-08-22, partner account: 11-1511-56120-11-0001, amount: 5000, and accounting date: 2026-08-18.

For this prompt, the assistant uses the joint venture, stakeholder, start date, partner account, and amount. It doesn't use the accounting date because that value isn't required from you for this task. For that parameter, the assistant uses the default value, which is the current date.