Create a Grade-Based Value by Criteria Definition for a Salary Basis Rate Definition

The grade-based performance award rate value identifies hourly workers with a grade of M1, M2, or M3 using value by criteria conditions.

  1. On the My Client Groups > Compensation page, click the Values Defined by Criteria task.
  2. On the Values Defined by Criteria page, create the Hourly Staff Performance Award value definition.
    1. On the Criteria and Values toolbar, click the Create icon.
    2. On the Create Values Defined by Criteria dialog box, complete the fields, as shown by these example values.

      Field Value
      Name Grade-Based Performance Award
      Effective Start Date 1/1/00
      Legislative Data Group US LDG
      Use existing range group Select
      Value Definition Group Any value, such as Workers Compensation
    3. Click OK.
  3. On the Create Values Defined by Criteria: Grade-Based Performance Award page, configure the value definition criteria.
    1. Select the Grade-Based Performance Award row.
    2. On the toolbar, click the New icon.
    3. On the Create Calculation Value Definition dialog box, select Criteria.
    4. Click OK.
    5. On the Create Criteria dialog box, complete the fields, as shown by these example values.

      Field Value
      Calculation Value Definition Name Pay Frequency
      Value Definition Group Any value, such as Performance Award
      Retrieval Date Effective Date
      Sequence 1
      Database Item Name PER_ASG_HOURLY_SALARIED_CODE
      Display Name Pay Frequency
      Operand =
      Literal Value H
    6. Click OK.
  4. On the Create Values Defined by Criteria: Grade-Based Performance Award page, create the M1, M2, and M3 criteria definitions.
    1. In the Criteria and Values table, expand the Grade-Based Performance Award row.
    2. Select the Pay Frequency = H row.
    3. On the toolbar, click the New icon.
    4. On the Create Calculation Value Definition dialog box, select Criteria.
    5. Click OK.
    6. On the Create Criteria dialog box, complete the fields, as shown by these example values.

      Field M1 M2 M3
      Calculation Value Definition Name Grade = M1 Grade = M2 Grade = M3
      Value Definition Group Any value, such as Performance Award Any value, such as Performance Award Any value, such as Performance Award
      Retrieval Date Effective Date Effective Date Effective Date
      Sequence 1 2 3
      Database Item Name PER_ASG_GRADE_NAME PER_ASG_GRADE_NAME PER_ASG_GRADE_NAME
      Display Name Grade Grade Grade
      Operand = = =
      Literal Value M1 M1 M1
    7. Click OK. Repeat these steps twice, to add the M2 and M3 calculation value criteria.
  5. On the Create Values Defined by Criteria: Grade-Based Performance Award page, create the M1, M2, and M3 value definitions.
    1. In the Criteria and Values table, expand the Grade-Based Performance Award row.
    2. Select the Grade = M1, M2, or M3 row.
    3. On the toolbar, click the New icon.
    4. On the Create Calculation Value Definition dialog box, select Value.
    5. Click OK.
    6. On the Create Value dialog box, complete the fields, as shown by these example values.

      Field Value M2 M3
      Calculation Value Definition Name M1 M2 M3
      Value Definition Group Any value, such as Workers Compensation Any value, such as Workers Compensation Any value, such as Workers Compensation
      Retrieval Date Effective Date Effective Date Effective Date
      Calculation Type Flat Amount Flat Amount Flat Amount
      Periodicity Annually Annually Annually
      Unit of Measure Money Money Money
      Currency USD USD USD
      Flat Amount 700 750 800
    7. Click OK. Repeat these steps twice, to add the M2 and M3 calculation value definitions.
  6. On the Create Values Defined by Criteria: Grade-Based Performance Award page, create the default criteria.
    1. Select the Grade-Based Performance Award row.
    2. On the toolbar, click the New icon.
    3. On the Create Calculation Value Definition dialog box, select Criteria.
    4. Click OK.
    5. On the Create Criteria dialog box, complete the fields, as shown by these example values.

      Field Value
      Calculation Value Definition Name Default Condition
      Value Definition Group Any value, such as Workers Compensation
      Retrieval Date Effective Date
      Default Criteria Select
    6. Click OK.
  7. On the Create Values Defined by Criteria: Grade-Based Performance Award page, review your value definition.
  8. When you're ready, click Submit.
  9. Click Done.