What's the precedence in which the Create Burden process checks the burden schedule to calculate burdening?

To calculate burdening, the Create Burden process checks:

  1. The burden schedule that's assigned to the award project top task.

  2. If no burden schedule is assigned to the award project top task, then it checks for the award project's override burden schedule.

  3. If no override burden schedule is assigned to the award project, then it checks for the award project's burden schedule.

  4. If no burden schedule is assigned to the award project, then it checks for the award's burden schedule.