How Resource Overall Match Score Is Calculated
The Resource Overall Match score is a measure of a resource's suitability to fulfill a project resource request.
How the Resource Overall Match Score Is Calculated
The Resource Overall Match score is the average of the Resource Available Capacity score and Resource Qualification score. For example:
![Resource Overall Match Score equals, left parenthesis, 50 percent plus, 80 percent, right parenthesis, divided by, 2, equals 65 percent.](images/prj_pjr_resourceoverallmatchscore65_20061315.png)
![Resource Overall Match Score equals, left parenthesis, 0 percent plus, 80 percent, right parenthesis, divided by, 2, equals 40 percent.](images/prj_pjr_resourceoverallmatchscore40_20061316.png)
If no Resource Qualification score exists, then the Resource Overall Match score is equal to the Available Capacity score.
If a resource doesn't have a valid calendar to calculate the Available Capacity score, then the Resource Overall Match score is the average of the Resource Qualification score and 0% for the Available Capacity score.