Configure Project Execution Management Applications

A project application administrator can add additional attributes to standard objects or create new custom objects to meet specific business needs using Application Composer. In Project Execution Management applications, using a sandbox, you can configure project resource requests, assignments, deliverables, issues, and backlog items.

For example, you can add an issue category attribute to drive additional information that you need to collect for a particular type of issue in the standard Issues object. You can also create a custom Risk object to capture and track risks.

After you create a custom object, you can:

  • Use the REST service to create, view, and update the custom object.

  • Create a new subject area to report on the custom object.

Since your organization can view the changes you make at runtime immediately, you must first create or select a sandbox and isolate your changes. A sandbox provides an independent development environment so that you can fully test your changes before publishing the sandbox and making the changes available to your organization.

Navigate to Application Composer from Tools and select ERP and SCM Cloud in the Application field. You can view the objects for Project Execution Management applications under Standard Objects menu.

Standard Objects Available for Configuration

The following table summarizes the objects, pages, and regions that you can configure. The objects listed here are available in Application Composer for configuration.

Standard Object

Corresponding Page or Region

Maximum Custom Attributes Allowed

Project Resource Assignments

  • Create Project Resource Assignment page in Project Resources work area
  • Edit Project Resource Assignment page in Project Resources work area

200 Number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

350 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

50 Time stamp (Any combination of Date, Date Time)

25 Clob (Any long text)

Project Resource Requests

  • Manage Project Resource Request page in Project Management work area

  • Manage Project Resource Request page in Project Resources work area

  • Create and Edit Project Resource Request page in Project Management work area

  • Create and Edit Project Resource Request page in Project Resources work area

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)

Project Issues

  • Create and Edit Issue page in My Work work area

  • Create and Edit Issue windows in Team Member Dashboard Issues section

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)

Project Deliverables

Create and Edit Deliverables page in My Work work area

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)

Backlog Items

Manage Backlog Items page

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)

Project Change Orders

  • Create Change Order page in both the Project Management and My Work work areas

  • Edit Change Order page in both the Project Management and My Work work areas

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)

Project Change Order - Impact Assessments

Add Impact and Edit Impact dialog boxes in both the Project Management and My Work work areas

50 number fields (Any combination of Number, Percentage, Currency, Dynamic Choice List)

100 Variable character fields (Any combination of Text, Check box, Fixed Choice List)

20 Time stamp (Any combination of Date, Date Time)