Example of Resource Actual Utilization Calculation

Actual utilization for the current quarter is the percentage of actual hours worked at the beginning of the quarter, plus projected project assignment hours from the date the process ran through the end of the current quarter, compared to the available hours.

Scenario

Following is an example of an actual utilization calculation for the current quarter.

Example scenario:

  • Resource name: Lisa Jones

  • Current quarter date range: January 1 - March 31, 2016

  • Today's date: February 15, 2016

  • Latest run date of the Update Resource Utilization Data process: February 15, 2016

  • Work category that is eligible for utilization: Project Work

  • Work categories that aren't eligible for utilization: Training and Paid Time Off

Lisa Jones is available to work for 8 hours a day, 5 days a week. Weekends are nonworking days.

The following table lists the actual, projected, and available hours in the current quarter for Lisa Jones. The table doesn't include weekend nonworking days.

Work Dates by Week

Work Category

Eligible for Utilization

Project Name

Worked Hours

Projected Hours

Available Hours

January 1 (holiday)

Not applicable

Not applicable

Not applicable

0

Not applicable

8

January 4-6

Project Work

Yes

Electrical

24

Not applicable

24

January 7-8

Training

No

Not applicable

16

Not applicable

16

January 11-15

Project Work

Yes

Electrical

24 (worked partial days)

Not applicable

40

January 18-22

Project Work

Yes

Hardware

40

Not applicable

40

January 25-28

Paid Time Off

No

Not applicable

32

Not applicable

32

January 29

Training

No

Not applicable

8

Not applicable

8

February 1-5

Project Work

Yes

Hardware

40

Not applicable

40

February 8-11

Project Work

Yes

Hardware

32

Not applicable

32

February 12

Project Work

Yes

Hardware

8

Not applicable

8

February 15-19

Project Work

Yes

Hardware

Not applicable

40

40

February 22-26

Project Work

Yes

Hardware

Not applicable

40

40

February 29-March 4

Not applicable

Not applicable

Not applicable

Not applicable

0 (no projected work)

40

March 7-11

Project Work

Yes

Install

Not applicable

40

40

March 14-18

Project Work

Yes

Install

Not applicable

40

40

March 21-25

Not applicable

Not applicable

Not applicable

Not applicable

0

40

March 28-31

Project Work

Yes

Launch

Not applicable

32

32

Results for the current quarter example:

  • Actual worked hours that are eligible for utilization: 168

  • Projected hours for project work: 192

  • Available hours: 520

The following formula calculates the resource actual utilization for this example.
Resource Actual Utilization equals, left parenthesis, 168 plus, 192, right parenthesis, divided by, 520, equals 69.23 percent.