Use prevalidation messages to identify errors that prevent export of your project plan from Microsoft Project to Project Management. You must fix all errors before exporting a project.

Identify tasks with prevalidation errors using the indicators in the Exception column in the Gantt Chart view of Microsoft Project.

Tip: After export, review the transfer report to identify if errors or warnings occurred for checks other than those performed during prevalidation.

Prevalidation Checks

The following table describes the prevalidation rules for tasks and resource assignments.

Level

Rule

Milestone tasks

No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks.

Milestone tasks

Milestone tasks must have zero duration.

Tasks Only existing labor resources in Project Enterprise Resources will be assigned as labor resources. Including the resource's email address is a best practice.