Which Dates Get Automatically Synchronized Between the Work Plan and Financial Plan?

If you've selected the Define Common Financial Task Dates Across Work and Financial Planning check box, only the financial task dates (Planned Start Date and Planned Finish Date) start getting automatically synced between a work plan and the corresponding financial plan.

The following don't sync:

  • Actual Start and Actual Finish: Dates when the task has actually started and finished.
  • Start and Finish dates: Current dates for the tasks. For not started tasks, they represent planned dates. For in-progress tasks, Start represents the actual start and Finish represents the estimated finish date. For completed tasks, they represent actual dates.
  • Baseline Start and Baseline Finish: Planned dates of the task when you created a baseline.