Calculate Project and Financial Plan Period Amounts Using Daily Spread Basis

Assign the Daily Spread Basis spread curve to a resource class or planning resource to proportionately distribute amounts across periods based on the ratio of the days in each period to the duration of the task assignment.

Settings That Affect Amount Distribution

You can't define spread points for the Daily Spread Basis spread curve. Therefore, distribution factors aren't calculated. Task assignment start and finish dates determine the number of days in each period, including the first and last periods, and consequently the allocation factor for each period.

Note: Assignment start and finish dates are included in the number of days in the period.

How Daily Spread Basis Amounts Are Calculated

When calculating period amounts, Oracle Fusion Cloud Project Management performs the following steps:

  1. Determines the number of days in the first and last period within the task assignment duration using assignment start and finish dates.

  2. Determines the number of days in the other periods within the assignment duration.

  3. Determines the total number of days for the duration of the task assignment.

  4. Calculates the allocation factor for each period using the following formula:

    period allocation factor = number of days in period / task assignment duration

  5. Calculates the periodic amount using the following formula:

    amount = period allocation factor * total resource cost or revenue

Example: Standard Accounting Calendar

In this example, a company uses an accounting calendar with periods that are identical to calendar months. A resource is assigned to a task for 121 days, from February 21 until June 21.

The following table shows how the task assignment days are determined, and the resulting allocation factors.

Month

Period Dates

Days in Period

Task Assignment Days

Period Allocation Factor

January

January 1 through January 31

31

0

0

February

February 1 through February 28

28

8

8 / 121 = 0.0661

March

March 1 through March 31

31

31

31 / 121 = 0.2561

April

April 1 through April 30

30

30

30 / 121 = 0.2479

May

May 1 through May 31

31

31

31 / 121 = 0.2561

June

June 1 through June 30

30

21

21 / 121 = 0.1735

121

121 / 121 = 1

Example: 4-4-5 Accounting Calendar

In this example, a company uses a 4-4-5 accounting calendar, with four weeks in the first and second months of the quarter, and five weeks in the third month of the quarter. A resource is assigned to a task from February 21 until June 21.

The following table shows how the task assignment days are determined, and the resulting allocation factors.

Month

Weeks in Period

Week Number

Ledger Start Date

Ledger End Date

Days in Period

Days in Ledger

Task Assignment Days

Period Allocation Factor

January

4

1

1

7

7

2

8

14

7

3

15

21

7

4

22

28

7

28

0

0

February

4

1

29

4

7

2

5

11

7

3

12

18

7

4

19

25

7

28

5

5 / 121 = 0.0413

March

5

1

26

4

7

2

5

11

7

3

12

18

7

4

19

25

7

5

26

1

7

35

35

35 / 121 = 0.2892

April

4

1

2

8

7

2

9

15

7

3

16

22

7

4

23

29

7

28

28

28 / 121 = 0.2314

May

4

1

30

6

7

2

7

13

7

3

14

20

7

4

21

27

7

28

28

28 / 121 = 0.2314

June

5

1

28

3

7

2

4

10

7

3

11

17

7

4

18

24

7

5

25

1

7

35

25

25 / 121 = 0.2066

121

121/121 = 1