Why can't I select an organization from the list of values on the Manage Project Costs page?

You must do the following to ensure that an organization displays in the Expenditure Organization choice list:

  1. Classify the organization as an expenditure organization.

  2. Assign the organization to the branch of the department or organization tree version used by the selected business unit.

  3. Flatten the department or organization tree version.

  4. Activate the department or organization tree version.

  5. Run the Maintain Project Organizations process.