The Project Enterprise Resource Calendars resource is used to view calendars of a Project Enterprise Resource which are single workday pattern and single shift. A calendar is used when scheduling or staffing a Project Enterprise Resource.
- Get a single shift resource calendar
- Method: getPath:
/fscmRestApi/resources/11.13.18.05/projectEnterpriseLaborResources/{projectEnterpriseLaborResourcesUniqID}/child/ResourceCalendars/{CalendarId}
- Get all single shift resource calendars used to schedule or staff a resource
- Method: getPath:
/fscmRestApi/resources/11.13.18.05/projectEnterpriseLaborResources/{projectEnterpriseLaborResourcesUniqID}/child/ResourceCalendars