Public Events for Project Execution Management

This table describes the public events supported by Project Execution Management.

Cloud Product

Supported Public Event

Description

Enabled by Default

First Release Available

Callback Service

Project Management Project Status Changes Signals whenever a project is created or a project status is changed. No 17D REST Service: Projects Operation: Get a Project

Project Management

Project Deliverable Status Changes

Signals whenever a project deliverable status or priority changes. Creating or deleting deliverables doesn't generate signals.

No

19A

REST Service: Deliverables

Method: Get a deliverable

Task Management

Project Task Progress Status Changes

Signals whenever a project task progress status changes. Creating or deleting tasks doesn't generate signals.

No

19A

REST Service: Project Plans

Resource: Tasks

Operation: Get a task of a project

Task Management

Project Milestone Completion

Signals whenever a project milestone is completed. Completing financial tasks that are flagged as milestones doesn't generate signals.

No

19A

REST Service: Project Plans

Resource: Tasks

Operation: Get a task of a project

Project Resource Management

Project Resource Request Status

Signals whenever the status of a project resource request changes, a new request is created in Open or Pending Adjustment status, or resource assignments are readjusted or canceled.

No

19B

REST Service: Project Resource Requests

Operation: Get a project resource request

Project Management

Project Gate Approver Status Change

Signals whenever the approval status for a gate is changed by an approver.

No

21C

REST Service: Project Plans

Resource: Tasks

Operation: Get a task of a project

Project Management

Project Gate Status Change

Signals whenever the status of a project gate is changed.

No

21C

REST Service: Project Plans

Resource: Gate Approvers

Operation: Update

Project Management

Project Change Order Changes

Signals whenever a project change order status or stage or priority changes. Creating or deleting change orders doesn't generate signals.

No

23D

REST Service: Change Orders

Resource: Change Order

Operation: Update

Project Management

Project Issue Status Changes

Signals whenever a project issue status or priority changes. Creating or deleting issues doesn't generate signals.

No

23D

REST Service: Project Issues

Resource: Project Issue

Operation: Update

Project Management

Project Work Plan Baseline Creation

Signals whenever a project work plan baseline is created. Setting an existing baseline as the primary baseline doesn’t generate signals.

No

23D

REST Service: Project Plans

Resource: Baselines

Operation: Create