Associate Asset Line Grouping Method with Project Types

Here's how you can associate project types with an asset line grouping method created using the Project Process Configurator.

  1. In the Setup and Maintenance work area, use the Manage Project Types task.

  2. On the Manage Project Types page, click the project type that you want to update.

  3. On the Edit Project Type page, click Capitalization Options.

  4. Click Asset Line Grouping Method in the Construction in Progress section and select Project Process Configurator.

  5. Click Save and Close.