Why are some of the expenditure items adjustments not processed?

Expenditure item adjustments aren't processed if:

  • The document entry of the expenditure item doesn't allow adjustments.

  • The Adjust transactions status control of project status doesn't allow transaction adjustments.

  • The expenditure item is already adjusted or reversed.

  • The expenditure item is a net zero expenditure item.

  • The same adjustment type for the expenditure item is already pending or rejected.

  • The expenditure item is marked as a converted transaction and the adjustment type is other than Edit Comment, or Hold and Release Invoice and Revenue.

  • You don't have the privilege to adjust.