How to Calculate Task Dates for New Projects
As a project manager, when creating a project, you can copy tasks from an existing project or a template. You can use the following applications to create projects and accordingly the dates are calculated and used.
Application |
Dates Used |
---|---|
Oracle Cloud Applications |
The application calculates planned dates for tasks and uses them in your project plan. They're based on dates you specify for the new project and the dates available in the source project. |
Microsoft Project |
The dates available in Microsoft Project are used. |
Settings That Affect Calculation of Task Dates
The task date calculation depends on:
-
Default settings in the project template
-
Settings in the project
-
Project details you enter in new project
How Task Dates Are Calculated
If you don't enter start and finish dates for your new project, then Project Foundation determines dates as follows:
-
If the project is created from a template, then the project start date is always the current date.
-
If the project is created from another project, then the project start date is the project start date of the source.
-
If tasks are defined in the source project, then the scheduled start date for the new project is derived from the rolled up task dates.
If you do enter a project start date, then Project Foundation shifts the task dates based on the difference between the dates of the source and the dates you specify for the new project. Consider the following example, where the task start and finish dates are pushed out 31 days based on the specified start dates.
Date Type |
Source Template Date |
Date Entered in Project Details |
Resulting Project Date |
---|---|---|---|
Project Start |
May 01, 2010 |
June 01, 2010 |
June 01, 2010 |
Project Finish |
May 31, 2010 |
NA |
July 01, 2010 |
Task Start |
May 02, 2010 |
NA |
June 02, 2010 |
Task Finish |
May 31, 2010 |
NA |
July 01, 2010 |
If you enter both a project start and finish date and the duration of the project is reduced, then task dates that are past the project finish date are truncated, as highlighted in the following example.
Date Type |
Source Template Date |
Date Entered in Project Details |
Resulting Project Date |
---|---|---|---|
Project Start |
May 01, 2010 |
June 01, 2010 |
June 01, 2010 |
Project Finish |
May 31, 2010 |
June 15, 2010 |
June 15, 2010 |
Task 1 Start |
May 01, 2010 |
NA |
June 01, 2010 |
Task 1 Finish |
May 15, 2010 |
NA |
June 15, 2010 |
Task 2 Start |
May 02, 2010 |
NA |
June 02, 2010 |
Task 2 Finish |
May 31, 2010 |
NA |
June 15, 2010 |