Why can't I edit the budgetary control settings for a budget version?

You can't edit the budgetary control settings for a budget version if one or both of the following conditions exist.

  • You don't have the necessary security privilege. Only the project manager and principal investigator can edit the budgetary control settings on a project.

  • A baseline version of the budget exists. After you create a baseline version of a budget, you can't edit the budgetary control settings.