Generate a Change Order from a Project Issue
You can generate a change order from a project issue using Oracle AI.
Project team members create issues as needed, which are then reviewed by the project manager. If a change order is needed, the project manager can generate it directly from the information in the issue and make changes.
- In the Project Management work area, open an issue.
- Click Initiate Change Order.
- Review the generated change order and update the details.
- Change the details or information in the issue and click Regenerate until you're happy with the generated change order.
- Save.
Results:
The change order includes the budget and forecast impact and also detailed impacts if there's a baseline budget version.