How can a resource manager adjust multiple resource assignments at the same time?
Select more than one confirmed or reserved assignment on the Manage Project Resource Assignments page, and click Adjust Assignment. Then select whether to change the assignment schedules as a group or individually.
-
To adjust the assignment schedule, enter a new start date, finish date, or hours per day and the adjustment reason in the Change Assignment Schedule window. If you're changing the assignment schedule for a group, you also have the option to move the start date and finish date by a specific number of working days. Then submit and approve the adjustments. The new values apply to all selected assignments.
-
To cancel assignments, enter the adjustment reason in the Cancel Assignments window, and then submit and approve the adjustments.
The application creates a project resource request for each adjusted assignment to communicate and track the adjustment approval.