Examples of Project and Task Codes
Project application administrators can manage project and task codes from the Manage Enterprise Project Codes page and the Manage Enterprise Task Codes page respectively.
Examples of Project Codes
Suppose your business needs project managers to capture savings that they must achieve on each negotiation made with a supplier and their actual savings for each project. In such cases, project application administrators can create the required custom attributes using project codes to capture the required values.
Here's a table that lists the custom attributes that must be created using project codes.
Data Type |
Project Code |
Column Name |
Column Description |
---|---|---|---|
Numeric |
Number 01 |
Sourcing Savings Goal |
The savings goal for your negotiation. |
Numeric |
Number 02 |
Sourcing Savings Goal (%) |
The savings goal for your negotiation in percentage. |
Numeric |
Number 03 |
Negotiated Savings |
The actual savings achieved for your negotiation. |
Numeric |
Number 04 |
Negotiated Savings (%) |
The actual savings achieved for your negotiation in percentage. |
After you create these attributes, project managers can enter values for these attributes when creating and managing projects.
Examples of Task Codes
Suppose project managers want to select a role required to perform each task before assigning resources to tasks. In such cases, project application administrators can create custom attributes using task codes to capture the values.
Here's a table that lists the custom attribute that must be created using task codes.
Data Type |
Task Code |
Column Name |
Column Description |
---|---|---|---|
Value Set |
List of Values 01 |
Role |
The role of the resource. |
And, here's a table that contains the values in the value set.
Sequence |
Value |
---|---|
1 |
Software Developer |
2 |
Project Manager |
3 |
Strategist |
4 |
Quality Analyst |
5 |
Information Developer |
After you create the Role value set, project managers can select a role when creating and managing tasks.