Why can't I find task assignments for a replacement resource?
While replacing a task assignment in the Replace Resource Assignments window, you entered a replacement date or period that is the same as or later than the planned finish date of the original resource.
Enter a replacement date or period that is earlier than the planned finish date of the original resource.