Why can't I edit the planning resources on a budget version?

After you create a baseline version of the budget that’s enabled for budgetary control, the names of existing planning resources become fixed. This is because these resource names are already integrated into the control budgets to create the control budget account segments.

Note:

You can add planning resources to the primary planning resource breakdown structure, and add the new resources to the working budget version.