Change Orders

Change orders are used to record, communicate, and track the impact of proposed project or nonproject changes.

You can perform a detailed impact assessment of planned amounts on a financial project plan by adding positive or negative resource amounts. The financial project plan is automatically updated when the Implementor selects Implement and Mark Complete. You can also assess the change order impact on the baseline project budget and then automatically generate a new baseline budget version when the change is implemented.

Project managers can generate a change order from an issue using Oracle AI by clicking Initiate Change Order in the issue. The generated change order includes budget and forecast impact, and it can include detailed impacts when a baseline budget version exists.

Project managers can also generate a summary for a saved change order. The summary highlights the financial impact of the change, helps reviewers and approvers understand the change more quickly, and appears in approval notifications. You can review and regenerate the summary after updating the change order details.

User Responsibilities

Project managers, project administrators, and team members can have the following user responsibilities.

User

Responsibilities

Creator

Creates the change order and names the owner.

Owner

  • Monitors the progress, resolution, implementation, and closure of a change order.

  • Adds and assigns roles to participants at any stage until the change order is either approved, closed, or canceled. This includes adding a participant for stages that have either been completed in the past or not yet visited.

  • Moves the change order to next or previous logical stage.

  • Removes participants on assigned tasks, if required.

Project Manager, Project Administrator Can change the owner of the change order.

Participant

Performs the assigned tasks. For example, the Reviewer reviews the change order and adds review comments and uploads attachments. An Implementor submits the change order for implementation.

Approver

Updates the progress and provides approval comments.

Stages and Statuses

Owners can control the progress of a change order throughout its lifecycle and change its stages. You can skip all stages except the Approval stage if an approver is added. The status of a change order automatically changes based on its stage.

Here's a table that contains the status, key owner and participant responsibilities, and next available action for each stage of a change order.

Note:
  • You can move to a stage only if participants are defined for that stage.

  • If you skip a stage, all defined participants for that stage will be removed.

Change Order Stage

Change Order Status

Description

Available Actions

Create

Draft

  • Stage and status after the creator initiates the change order.

  • Owner enters change order details and assigns participants to assess, review, approve, and implement the change order.

For change owner:
  • Edit change order

  • Cancel change order

  • Close change order

  • Delete change order

  • Submit for impact assessment

  • Submit for review

  • Submit for approval

  • Submit for implementation

Impact Analysis

In Progress

  • Stage and status after the owner submits the change order for impact assessment.

  • Owner who adds an impact is added as an Assessor by default.

  • Assessors are added as Implementors by default. However, owner can remove them from this role.

  • Assessor adds, edits, or deletes impacts added by self while owner can update impacts of other participants too.

  • Assessor adds impacts for resource assignments in positive or negative quantities. Rate schedules are used to compute raw cost and revenue, which can also be manually entered.

For assessors:
  • Mark complete
For change owner:
  • Edit change order

  • Cancel change order

  • Close change order

  • Submit for review

  • Submit for approval

  • Submit for implementation

Review

In Progress

  • Stage and status after the owner submits the change order for review.

  • Reviewer adds review comments and uploads attachments.

For reviewers:
  • Mark complete
For change owner:
  • Edit change order

  • Cancel change order

  • Submit for impact assessment

  • Submit for approval

  • Submit for implementation

Approval

In Progress

  • Stage and status after the owner submits the change order for approval.

  • Approver updates the progress and provides approval comments.

  • All Approvers must approve the order before the owner can submit the order for implementation or close the order.

  • The owner can't skip an Approver. However, the owner can delete Approvers who don't respond.

For approvers:
  • Approve
  • Reject
For change owner:
  • Edit change order

  • Cancel change order

  • Close change order

  • Submit for impact assessment

Approval

Approved

Stage and status after all Approvers approve the change order.

For change owner:
  • Submit for impact assessment

  • Submit for review

  • Submit for implementation

  • Close change order

  • Cancel change order

Approval

Rejected

  • Stage and status after an Approver rejects the change order.

  • Approver specifies rejection reason and comments.

For change owner:
  • Submit for impact assessment

  • Submit for review

  • Cancel change order

Implementation

Approved

  • Stage and status after the owner submits the change order for implementation.

  • Implementor updates the comments and attachments.

  • Implementor can automatically generate a new baseline budget version incorporating the change impact when detailed budget impacts are documented in the change order.

  • When detailed project plan impacts are documented, the implementors can include the changes in the financial project plan during implementation.

For implementor:
  • Mark complete
  • Implement and mark complete (if the change order has a detailed budget or project plan impact)
For change owner:
  • Submit for impact assessment

  • Submit for review

  • Submit for approval

  • Close change order

  • Cancel change order

After automatic implementation of a change order with detailed budget impacts Close Change Order is the only action available.

Close

Completed

Stage and status after the owner closes the change order.

For change owner:

Close change order

Cancel

Canceled

  • Stage and status after the owner cancels the change order.

  • Owner specifies cancellation reason and comments.

For change owner:

Cancel change order

Project managers can generate a change order from an issue and associate a task with a change order to efficiently track tasks and analyze change orders. Keep in mind that you can't delete a task that's associated with a change order.