Configure Labor Resource Requests and Staffing

Configure Project Labor Resource Request Policy to evaluate and fulfill labor resource requests.

Project Planning Workspace derives the applicable business unit from the logged-in user’s business-unit assignment in HCM. Create a Default configuration, and create business-unit-specific configurations when staffing rules differ. If no business-unit-specific configuration applies, the workspace uses the Default configuration.

Configure Resource Pool Ownership

Assign each workspace user as the Owner of the applicable resource pool before they perform resource matching, resource-request fulfillment, or staffing.

  1. In the Setup and Maintenance work area, search for and open the Manage Resource Pools task.
  2. Select the applicable resource pool.
  3. Assign the workspace user as the resource pool owner.

A Pool Manager assignment doesn’t satisfy the resource pool ownership requirement. Access to fulfill resource requests is scoped by the resource pools that the user owns.

Configure Labor Resource Request Policy

The Project Labor Resource Request Policy has one customer-editable configuration attribute: Qualification Threshold. This threshold determines the minimum qualification score that a person must meet before being considered for assignment.

Configuration Attribute

Purpose

Value

Allowed Values

Qualification Threshold

Minimum qualification requirement before a person is considered for assignment.

Enter the approved threshold.

0% to 100%

Resource matching applies to approved, time-phased labor demand that remains planned by role or job. The project plan must use an eligible primary project resource breakdown structure (PRBS). Complete the applicable labor resource request and staffing prerequisites before starting resource matching.

How Labor Matching and Staffing Works

When a Project Manager starts resource matching, the workspace evaluates the approved, time-phased labor demand and project-role requirements. It uses available matching evidence to identify qualified people with capacity.

After the required project decision, the workspace creates named-person plan assignments. It replaces the applicable role or job hours with named-person hours and reconciles the assignments by task and period without changing the approved demand.

If required policy information, project setup, or matching evidence is missing, the workspace suppresses the affected action and identifies the configuration or data gap.