Examples of Configuring Project Planning Workspace

These illustrative examples show how policy values can affect workspace behavior. Replace the sample values with values approved by your organization.

Calculate an Opportunity Cost Estimate

This example uses illustrative effort standards and a delivery-cost rate. Replace these values with the approved standards for your organization.
  1. Select the Estimation policy cost-estimation method.
  2. Configure a mobilization effort of 160 hours per functional workstream and a Functional Workstream standard of 500 hours per workstream.
  3. Configure a delivery cost rate of USD 150 per hour.
  4. Configure a project margin of 20%.
  5. Configure an opportunity threshold for proposal generation of 70%.
  6. Save the policy configuration.
  7. Create an Oracle Sales opportunity with a win probability of 70% or higher. Attach a supporting RFP that identifies two functional workstreams.
  8. Review the calculated effort, cost estimate, and revenue estimate.

Expected result: The workspace identifies the two functional workstreams in the supporting RFP. It calculates 320 mobilization hours (160 hours × 2 workstreams) and 1,000 Functional Workstream hours (500 hours × 2 workstreams), for a total of 1,320 hours. At USD 150 per hour, the estimated cost is USD 198,000. With a 20% margin, the workspace derives a revenue estimate of USD 247,500. If the calculated margin doesn’t meet the configured requirement, the workspace displays the shortfall or prevents the estimate from proceeding, according to the configured policy.

Make a Sales Opportunity Available for Project Creation

  1. For the Services business unit, set the opportunity status for project creation to Won.
  2. Set the opportunity threshold for project creation to 70%.
  3. Set the High priority window to apply when the required action is due within 10 days.
  4. Save the policy configuration.
  5. Create an Oracle Sales opportunity for the Services business unit with a status of Won and a win probability of 70% or higher.

Expected result: Project Planning Workspace makes project creation available for review. If the action is due within 10 days, it is assigned High priority according to the configured priority window. If the opportunity win probability is below 70%, the workspace does not make the project-creation action available.

Create a Detailed Budget with a Reserve

  1. Configure a reserve percentage of 10%.
  2. Set reserve placement to the project level.
  3. Select the configured reserve resource.
  4. Select the Reference Project Method detailing method.
  5. Configure the reference-project matching and ranking rules.
  6. Save the policy configuration.
  7. Open a project with an approved strategic budget.
  8. Review the reference project selected by the workspace, the prepared allocations, reserve, revenue target, and margin.
  9. Review any phase, task, resource, margin, or reserve exceptions, and resolve them when required by the configured policy.
  10. Recalculate the allocation and confirm it before applying the permitted writeback action.

Expected result: The workspace calculates the reserve before distributing the remaining approved budget and prepares a policy-guided allocation for review. When an exception exists, the workspace displays the configured warning or revision requirement before the writeback action can proceed.

Create a Project and Associated Contract Information

  1. Create or update the applicable Default configuration or business-unit-specific configuration for project creation.
  2. Set the default budget creation preference to Generate by default.
  3. Set the default contract creation preference to Yes.
  4. Set the contract creation method to Create a new contract.
  5. Select the approved contract creation source.
  6. Set the contract amount association level to Task level.
  7. Set the task-level distribution method to Selected top-level tasks.
  8. Save the policy configuration.
  9. Create a project from an eligible opportunity or supporting document.
  10. Review the project draft, including template defaults, validated source information, budget treatment, and contract treatment.
  11. Confirm the project draft.

Expected result: Project Planning Workspace derives the applicable business unit from the user context and applies the matching business-unit-specific configuration or Default configuration. The workspace creates the project only after the user confirms the draft.

Staff Approved Labor Demand

  1. Configure a qualification threshold of 80%.
  2. Save the policy configuration.
  3. Open approved, time-phased labor demand planned by role or job, with a qualified person who has available capacity.
  4. Review the candidate evidence and confirm the staffing result when required.
  5. Confirm that the workspace creates named-person demand and reduces the corresponding role or job demand.
  6. Open another labor-demand scenario with no suitable person available.

Expected result: The workspace identifies a person who meets the 80% qualification threshold and has available capacity. When staffing is completed, the workspace creates named-person demand and reduces the corresponding role or job demand. When no suitable person is available, the workspace opens an email communication with the resource-request details.