Request and Staff Labor Resources

Persona: Project manager

Trigger: Approved, time-phased labor demand planned by role or job is ready for matching.

Interaction: The Project Planning Workspace evaluates available candidates against role qualifications, project-specific skills, location, capacity, and policy requirements. When a candidate meets the configured policy conditions, the workspace automatically assigns the qualified person to the approved labor demand.

Expected result:The workspace creates named-person demand and reduces the corresponding role or job demand.

Human review: Review and accept exceptions, such as a candidate who doesn’t meet the configured policy conditions. Review and send the resource-request communication when no suitable person is available.

Confirm the resulting named-person demand and corresponding role or job-demand reduction before considering staffing complete.

Exception path: When no suitable person is available, the workspace opens an email communication with the resource-request details. Recruiting, hiring, and worker-assignment activities occur outside the workspace flow.