Enhanced Highlighting in Gantt Chart
This enhancement enables users to easily identify specific work order operations through enhanced Gantt highlighting. Examples include work order operations pegged to material shortages, those offloaded to alternate resources, or those belonging to work orders in released status.
Previously, you could highlight operations in the Gantt chart that belonged to firm work orders or late work orders. With this update, you can now also highlight work order operations with these properties:
- Fixed start time: Work order operations with firm status set to fixed start time.
- Offloaded to alternate resource: Work order operations that were offloaded from the primary resource and are now scheduled on an alternate resource.
- Offloading allowed: Work order operations that can be offloaded.
- Pegged to shortage: Work order operations that are pegged to a shortage amount of a component item.
- Released: Work order operations that belong to released work orders.
You can use the various highlight capabilities in conjunction with other schedule analysis features to better understand the production schedule. For example, the user highlights all work order operations in the Gantt chart that are pegged to an inventory shortage amount. User then activates the Filter By Gantt Chart Selection mode, and selects an operation to see which specific items with shortage are pegged to that operation.
Steps to Enable
Use the Opt In UI to enable this feature. For instructions, refer to the Optional Uptake of New Features section of this document.
Offering: Supply Chain Planning
Tips And Considerations
If you want to use the Enhanced Highlighting in Gantt Chart feature, then you must opt in to its parent feature: Production Scheduling. If you’ve already opted in to this parent feature, then you don’t have to opt in again.
Key Resources
- Visit https://redwood.oracle.com/ for more information about the Redwood experience.
Access Requirements
Users who are assigned a configured job role that contains this privilege can access this feature:
- Edit Production Schedule (MSC_EDIT_PRODUCTION_SCHEDULE_PRIV)
This privilege was available prior to this update.