This example describes a scenario where transactions for a contract line need to be invoiced and the revenue recognized using the percent spent method.

The following table summarizes key decisions for this scenario.

Decisions to Consider

In This Example

What are the revenue and invoice method classifications?

Percent Spent

What is the billing extension calculation level for the contract line and project association?

Project level

Summary of the Tasks

Create a contract, create the percent spent contract lines, create the bill plan, create the revenue plan.

Prerequisites

  1. Create a project.

  2. Create a financial project plan for the project.

  3. Specify the desired cost plan type on the percent spent invoice or revenue billing extension.

  4. If the class of the selected cost plan type is:

    • Budget: create a project budget, set as current working, and create a baseline.

    • Forecast: create a project forecast, set as current working, and approve.

  5. Enter labor and expense transactions for the project.

  6. Collect costs for the transactions.

Creating the Contract

  1. On the Contract Overview page, expand Search and look for the contract with the attributes listed in the following table.

    Field

    Value

    Contract Type

    Sell: Project Lines

    My Contracts

    If this field is checked, remove the check mark.

    Party Name

    Vision Software Install

  2. Click Search.

  3. In the Search Results region, select the row for the PJB contract (VO), Version 1.

  4. Click Actions > Duplicate.

  5. On the Duplicate Contract window, enter the values listed in the following table.

    Field

    Value

    Contract Number

    Your initials, PS001 (For example, TP PS001)

    Start Date

    01/01/2010

    All other fields

    Enable check boxes

  6. Click Yes.

Creating the Percent Spent Contract Lines

  1. Select the Lines tab, and select the Amount Based Invoice, Percent Spent Revenue row. Confirm the amount is $250,000.

  2. Select the Billing tab, and select the row with the $250,000 soft limit.

  3. Click Resource Member, and select Labor (Expenditure Category).

  4. Click the Create icon. Click Resource Member, and select Expenses.

  5. Enter 30,000 for Soft Limit.

  6. Click Save.

  7. Select the Associated Projects tab, and the Create icon.

  8. Enter the information listed in the following table.

    Field

    Value

    Project Name

    Select the project you created in the earlier example.

    Funded Amount

    100,000

  9. Click Save.

Creating the Bill Plan

  1. Select the Header tab, and click Billing.

  2. Select the row with the BP PS1 Bill Plan.

  3. Verify the information described in the following table.

    Field

    Value

    Method Name

    Percent Spent

    Billing Cycle

    Last Day of the Month

  4. In the Associated Contract Lines region, select the Add icon.

  5. In the Select and Associate: Contract line window, click Search.

  6. Select the row containing Contract Line Number 4.

  7. Click Submit.

  8. Click Save.

  9. Select the Billing Extensions tab.

  10. Verify the information described in the following table.

    Field

    Value

    Name

    Percent Spent Invoice

    Status

    Active

    Calculation Level

    Associated Project

  11. Click Save and Close.

Creating the Revenue Plan

  1. From the Header tab, click Billing.

  2. Select the row with the RP PS1 Revenue Plan.

  3. Verify if the following information is present:

    Field

    Value

    Method Name

    Percent Spent Revenue

    Contract Line Number

    4

  4. Select the Billing Extensions tab.

  5. Verify the information described in the following table.

    Field

    Value

    Name

    Percent Spent Revenue

    Status

    Active

    Calculation Level

    Associated Project

  6. Click Save and Close.