Create Contract for Percent Spent Invoice and Revenue Methods
This example describes a scenario where transactions for a contract line need to be invoiced and the revenue recognized using the percent spent method.
The following table summarizes key decisions for this scenario.
Decisions to Consider |
In This Example |
---|---|
What are the revenue and invoice method classifications? |
Percent Spent |
What is the billing extension calculation level for the contract line and project association? |
Project level |
Summary of the Tasks
Create a contract, create the percent spent contract lines, create the bill plan, create the revenue plan.
Prerequisites
-
Create a project.
-
Create a financial project plan for the project.
-
Specify the desired cost plan type on the percent spent invoice or revenue billing extension.
-
If the class of the selected cost plan type is:
-
Budget: create a project budget, set as current working, and create a baseline.
-
Forecast: create a project forecast, set as current working, and approve.
-
-
Enter labor and expense transactions for the project.
-
Collect costs for the transactions.
Creating the Contract
-
On the
page, expand Search and look for the contract with the attributes listed in the following table.Field
Value
Contract Type
Sell: Project Lines
My Contracts
If this field is checked, remove the check mark.
Party Name
Vision Software Install
-
Click Search.
-
In the Search Results region, select the row for the PJB contract (VO), Version 1.
-
Click
. -
On the Duplicate Contract window, enter the values listed in the following table.
Field
Value
Contract Number
Your initials, PS001 (For example, TP PS001)
Start Date
01/01/2010
All other fields
Enable check boxes
-
Click Yes.
Creating the Percent Spent Contract Lines
-
Select the Lines tab, and select the Amount Based Invoice, Percent Spent Revenue row. Confirm the amount is $250,000.
-
Select the Billing tab, and select the row with the $250,000 soft limit.
-
Click Resource Member, and select Labor (Expenditure Category).
-
Click the Create icon. Click Resource Member, and select Expenses.
-
Enter 30,000 for Soft Limit.
-
Click Save.
-
Select the Associated Projects tab, and the Create icon.
-
Enter the information listed in the following table.
Field
Value
Project Name
Select the project you created in the earlier example.
Funded Amount
100,000
-
Click Save.
Creating the Bill Plan
-
Select the Header tab, and click Billing.
-
Select the row with the BP PS1 Bill Plan.
-
Verify the information described in the following table.
Field
Value
Method Name
Percent Spent
Billing Cycle
Last Day of the Month
-
In the Associated Contract Lines region, select the Add icon.
-
In the Select and Associate: Contract line window, click Search.
-
Select the row containing Contract Line Number 4.
-
Click Submit.
-
Click Save.
-
Select the Billing Extensions tab.
-
Verify the information described in the following table.
Field
Value
Name
Percent Spent Invoice
Status
Active
Calculation Level
Associated Project
-
Click Save and Close.
Creating the Revenue Plan
-
From the Header tab, click Billing.
-
Select the row with the RP PS1 Revenue Plan.
-
Verify if the following information is present:
Field
Value
Method Name
Percent Spent Revenue
Contract Line Number
4
-
Select the Billing Extensions tab.
-
Verify the information described in the following table.
Field
Value
Name
Percent Spent Revenue
Status
Active
Calculation Level
Associated Project
-
Click Save and Close.