How do I use the Demand Cutoff Date and Demand Cutoff Date Offset parameters for the Min-Max Planning Report?

The Demand Cutoff Date tells the application to consider demand up until the particular date that you enter.

The value that you enter for the Demand Cutoff Date Offset is used by the application to consider demand within the current date minus the offset number of days that you specify. Let's say you enter a value of 2 for the Demand Cutoff Date Offset. The application considers demand within the current day minus two days.

For example, consider the values in this table:

Field

Value

Demand Cutoff Date

25-Jan

Current Date

31-Jan

Demand Cutoff Date Offset

2

The Min-Max Planning report runs for all demand between 25-Jan to 29-Jan (31-2=29).