Import Collaboration Order Forecasts
Use this process to import the collaboration order forecasts into the Supply Chain Collaboration interface tables from an external application when using the Load Interface File for Import scheduled process as part of the File-Based Data Import (FBDI) mechanism.
When to Use
The Import Collaboration Order Forecasts scheduled process is the import process that
loads collaboration order forecasts from FBDI files when you use the Load Interface
File for Import scheduled process. When using the Import Collaboration Order
Forecasts scheduled process, first select the Load Interface File for Import
scheduled process, and then select the previously loaded data file that was uploaded
using the scm/collaborationOrderForecast/import
account from the File Import and
Export page.
For more information on the FBDI mechanism, see File-Based Data Import (FBDI) for SCM.
Privileges Required
- Import Collaboration Order Forecasts (VCS_COLLABORDERFORECAST_IMPORT_PRIV)
Specifications
Review these specifications before setting up this scheduled process:
Specification | Description |
Job Type | Submitted on a spontaneous basis if required. |
Frequency | As required by your business, usually after your planning cycle ends. |
Time of Day | After work hours is recommended but can be submitted any time based on your requirements. |
Duration | Run time for the process varies and depends on the number of forecast records that must be processed. |
Compatibility | There are no compatibility issues with other scheduled processes. |
Parameters
There aren't any parameters for this scheduled process.
Troubleshooting Information
- You can view the status of the process on the Scheduled Processes UI. A succeeded status indicates that the process has completed successfully.
- Validation errors and warning messages that prevented this scheduled process from
completing successfully display in the error log. Note: Collaboration relationships and a collaboration plan must already exist in order to load the data into the interface tables successfully.
- The process does not perform interactive warning validations.
- After you submit the scheduled process, you cannot perform any of these tasks in
the Scheduled Processes UI:
- Resubmit it
- Put it on hold
- Cancel the process
- Release the process