How is the due date on the Cycle Count Listing report calculated?

When the count sequence is generated, that date is added to the value in the Maximum Days Before Late field. If the date is a non-working day, then the next working day date is used.

For example, if the workday schedule is Monday through Thursday (July 18 through July 21), counts are generated on Thursday (July 21). If the maximum number of days before late is 3, then the due date would be Sunday (July 25). However, as Sunday is off, the count date will be stamped with Monday’s date (July 26).