Refresh and Solve Actions
Use the Refresh action to update your schedule data, such as work order data, attribute data, and resource capacity and availability. You can refresh a schedule at any time.
-
A refresh discards the existing scheduling solution to make way for the new data, so if you need to retain an existing solution, release the schedule before refreshing it.
-
A schedule refresh updates the schedule with new data from Oracle Fusion Cloud Manufacturing. When you set the resource parameter mode to constrained or relaxed for capacity only, the calendar events are taken into account when refreshing and the work order operations may be moved. But if you choose relaxed mode, the calendar events are ignored and work order operations are as retrieved from Oracle Fusion Cloud Manufacturing.
- Pegging links are accurate only after a solve action.
If you want the solver to automatically generate a new solution after a refresh, click Refresh and Solve.