Collect Data Using the Net Change Collection Type

You can collect data from the Oracle Fusion source system by running the net change collection or by scheduling to run the process later.

Before running a Net Change collection, you must run a Targeted collection for the selected entities. After the first Targeted collection, you can run Net Change collections.

Perform the following procedure to collect reference data and supply planning data using the net change collection type:

  1. If you are in one of the Supply Chain Planning work areas, then click the Tasks panel tab. In the Tasks panel drawer, click the Collect Planning Data task. If you are in the Setup and Maintenance work area, then use the following:

    • Offering: Supply Chain Planning

    • Functional Area: Supply Chain Planning Configuration

    • Task: Collect Planning Data

  2. Complete the following parameters for the Collect Planning Data process:

    1. Select your source system.

    2. Select the collection type as Net change.

      Note: You cannot make any changes to the filter criteria and demand planning data in the net change collection type.
    3. In the Reference Data tab, move the required reference entities to the Selected Entities area.

    4. In the Supplies Planning Data tab, move the required supply entities to the Selected Entities area.

  3. (Optional) Click the Schedule tab and set collections to run as soon as possible or schedule to run at a different time.

  4. Click Submit to initiate the collections process.

  5. Monitor the collection status using the Scheduled Processes page.

  6. Review the collected data in the Plan Inputs work area.