Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data

The Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process is a child process of the parent Aggregate Collected Planning Data scheduled process. The child process is automatically started by the parent process.

The Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process aggregates measure data for the planning level profiles selected in the parent scheduled process.

When to Use

When you submit the parent Aggregated Collected Planning Data scheduled process, it automatically calls the Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process.

The Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process is run after the Aggregate Collected Planning Data: Create Snapshot of Aggregated Dimension Data scheduled process is run. The Aggregate Collected Planning Data: Create Snapshot of Aggregated Dimension Data scheduled process is also submitted by the parent scheduled process.

In the Scheduled Processes work area, you can't select and submit the Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process.

Privileges Required

  • Run Plan with Snapshot (MSC_RUN_PLAN_WITH_SNAPSHOT_PRIV, for the parent scheduled process)

Specifications

Not relevant, because the child scheduled process is automatically submitted by the parent scheduled process when you run it.

Parameters

Parameter Optional or Required Description Parameter Value Special Combinations Required Notes
Profile ID Required ID of the planning level profile The ID of the planning level profile submitted through the parent scheduled process None The user can't select the parameter because the child scheduled process is submitted by the parent scheduled process.
Measure ID Required ID of the measure for data aggregation The ID of the measure None The user can't select the parameter because the child scheduled process is submitted by the parent scheduled process.
Mode Required The type of the run for the scheduled process
  • 1 (Targeted)
  • 2 (Net change)
None The user can't select the parameter because the child scheduled process is submitted by the parent scheduled process.
Note: If you select a planning level profile for the Aggregate Collected Planning Data scheduled process, an instance of the Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process is submitted for each combination of the planning level profile and a measure. If you select ALL for the Aggregate Collected Planning Data scheduled process, an instance of the Aggregate Collected Planning Data: Create Snapshot of Aggregated Measure Data scheduled process is submitted for each combination of a planning level profile in the Enabled or Ready status and a measure.

Troubleshooting Information

  • You can view the status of the scheduled process on the page for scheduled processes.
  • If the scheduled process takes a long time to run, click the Cancel Process button.
  • The errors and warnings for the scheduled process are displayed in a log file.

    No warnings are displayed for you to perform actions while the scheduled process is running.

  • If the scheduled process isn't successfully run, review the error messages in the log file.

    If the reason for the failure isn't clear, review the diagnostic log files with the help of My Oracle Support.