Print Electronic Production Records
Use the Print Electronic Production Records scheduled process to generate a summary of a product's production record based on its work order, including its complete production and quality history.
- You can run this scheduled process from the Work Execution work area task list to print production records for a single work order or for multiple work orders.
- You also can run this process directly from the Scheduled Processes work area.
- You can run the process only when work orders are in either a closed or a completed status.
- The process uses a default template to generate the documents.
You can configure the template to add or remove attributes from the predefined attribute list, or to change the layout of the report.
When to Use
Run this scheduled process only after you ensure that the manufacturing work order for a given product is in either a closed or completed status.
Privileges Required
- Print Electronic Production Records (WIP_PRINT_ELECTRONIC_PRODUCTION_RECORDS_PRIV)
Specifications
Specification | Description |
Job Type | Scheduled or as needed. |
Frequency | As required. |
Time of Day | Any time. |
Duration | Varies, based on the volume of data records. |
Compatibility | There can be multiple instances running at the same time for separate work orders. |
Parameters
Parameter | Optional or Required | Description | Parameter Value | Special Combinations Required |
Organization | Required | Organization Code | Example: ORG1 | None |
From Work Order | One of the two parameters is required | From work order number | Example: WO1001 | None |
To Work Order | One of the two parameters is required | To work order number | Example: WO1002 | Defaulted from ‘From Work Order’ |
Work Order Status | Required | Status of the Work order | All applicable seeded and custom work order statuses | None |
Troubleshooting Information
- You can view the status of the Print Electronic Production Records process in the Scheduled Processes work area.
- Any report-generation errors will display in error log.
- After you submit the scheduled process, you can perform any of these tasks in
the Scheduled Processes work area:
- Resubmit it
- Put it on hold
- Cancel it
- Release it