Split Order Lines Based on Organizations
If a backlog plan is run and the requested supply for an order is available across two or more ship-from organizations, the order lines are split based on the organizations and planned on the requested date.
You can split the order line and plan supply from up to 10 different ship-from organizations.
Before running the backlog plan and splitting the order lines based on organization, clear the value of the Requested Ship from Organization field for the order lines that need to undergo splitting.
Let’s take an example where to fulfill an order of 100 units, the supply is taken from three organizations M1, M2 and M3. Here is what the availability of supply in these organizations looks like:
Item | Organization | Quantity | Supply Availability Date |
---|---|---|---|
Item1 | M1 | 50 | 1/7/2030 |
Item1 | M2 | 30 | 1/7/2030 |
Item1 | M3 | 20 | 1/7/2030 |
In this case, the order is split into three order lines and the order is fulfilled on 1/7/2030.