Enable Multiechelon Planning for Your Replenishment Plan

You enable multiechelon planning for your replenishment plan using the Plan Options page.

  1. On the Plan Options page for your replenishment plan, click the Supply tab.
  2. Click the General subtab.
  3. In the Multiechelon Plan Attributes section, select the Enable multiechelon planning check box.
  4. Save your work.

Results:

Multiechelon planning is done for your replenishment plan when you run it.