How Items Are Set Up

The items used in contract manufacturing are created in the Product Information Management work area. The following key setup tasks are performed within the Product Information Management work area:

  • Create Items setup is used to create items such as the contract manufacturing finished goods item and the contract manufacturing service item. It is also used to set the attributes as required for the contract manufacturing flow.

  • Create Item Structure setup is used to create the bill of material for the contract manufacturing finished good item.

The following table displays items and the attributes for Finished Goods item, original equipment manufacturer (OEM) supplied components, contract manufacturer supplied components, and contract manufacturing service item (represented as Contract Manufacturer Finished Goods Server):

Attribute Name

Attribute Value

Attribute Value

Attribute Value

Attribute Value

Not Applicable

Finished Goods Server

Contract Manufacturer Finished Goods Server

OEM Components

Contract Manufacturer Sourced Components

Item Type

Make

Buy

Transfer

Transfer

Inventoried

Yes

Yes

Yes

Yes

Stockable

Yes

Yes

Yes

Yes

Transactable

Yes

Yes

Yes

Yes

Back-to-Back

Yes

No

No

No

Contract Manufacturing

Yes

Yes

No

No

Inventory Planning Method

Not Planned

Not Planned

Min-Max Planning (for pre-positioned components)

Not Planned

Planning Method

Not Planned (for Back-to-Back) and MPS Planning (for Plan to Produce)

Not Planned

MRP Planning (for components supplied per order)

Not Planned

Supply Type

Push

Assembly Pull

Push

Supplier

If you've defined the contract manufacturing finished goods item as a dual units of measure item, which means the Tracking Unit of Measure is set to primary and secondary, you should also define the contract manufacturing service item as a dual units of measure item.

The contract manufacturing service items set up with defaulting control as Fixed and Default are supported, whereas No Default isn't supported. You're not allowed to create a contract manufacturing service item with defaulting control No Default in Product Information Management. It's also recommended that if both the contract manufacturing finished goods item and contract manufacturing service item are dual units of measure items, then you should set up their secondary UOM, positive and negative deviation factors, and item intraclass and interclass conversions identically. The application doesn't enforce these validations.

For general details about setting up items and setup steps common to all SCM offerings, refer to the Implementing Common Features for SCM guide.