How the Replenishment Date is calculated

Count only work days to calculate the Replenishment date.

Oracle uses the following logic to calculate the Requested Delivery Date to Min Max Program.

System Date + Preprocessing (Days) + Processing (Days) = Requested Delivery Date

Note: The Min-Max program counts only the work days to derive Requested Delivery Date.

For example:

If the Requested Date is 08/01/24 + Preprocessing (2 Days) + Processing (8 Days), the Requested Delivery Date will be 08/13/24. Only work days are counted to calculate the Requested Delivery Date.