Why isn't the min-max report creating any requisitions?

Min-max planning should create requisitions for min-max planned items that have their source type set as Supplier.

Ensure that you have set the item sourcing details type to Supplier:

  1. In the Setup and Maintenance work area, go to the Manage Inventory Organization task.

    • Offering: Manufacturing and Supply Chain Materials Management

    • Functional Area: Facilities

    • Task: Manage Inventory Organization

  2. Search for the organization for which min-max requisitions aren't creating correctly.

  3. Click the Manage Inventory Organization Parameters button.

  4. Click the Item Sourcing Details tab.

  5. Under the Item Sourcing Details section, select Supplier in the Type field.

Verify that requisitions are now being created:

  1. Create a min-max item.

  2. Run the Min-Max Planning report.

  3. Submit the Process Supply Chain Orchestration Interface scheduled process.