Rollups in Concept Design

Analyze concepts, concept components, and items scores after a roll-up of their target and actual attributes across cost, weight, and power consumption.

You can roll-up values of cost, weight, power, and score attributes, using the Calculate icon in the Edit Concept page. The roll-up values are best viewed in the Metrics view of the concept structure.

Cost Rollup

The Total Cost of a concept, described in the following table, is calculated as an aggregate of total costs of its individual concept components, items, assemblies, and embedded concepts.

Element

Total Cost Calculation

Notes

Component

(Material Cost + Nonmaterial Cost) * Quantity

None

Item

(Material Cost + Nonmaterial Cost) * Quantity

If an item has BOM, only the cost of parent item is considered for rollup.

Assembly Component

(Total cost of each child element) + Nonmaterial Cost at assembly level

Any manually-entered cost value at the assembly level is replaced by the calculated cost value of a rollup.

Embedded Concept

Rolled-up cost of concept * Quantity

You must roll up the embedded concept by opening the concept separately and performing the roll up there, before other roll-ups, otherwise the cost calculation is zero.

Concept

Aggregate of total cost of each assembly or element in root-node

Element refers to a Component, Item or Embedded Concept.

Weight and Power Roll-Up

The Total Weight and Total Power of a concept, described in the following table, are calculated as aggregates of respective roll-up values of its individual concept components, items, assemblies, and embedded concepts. Weight and power attributes are subject to identical roll-up logic.

Element

Total Weight or Total Power Calculation

Notes

Component

Weight or Power of Component * Quantity

None

Item

Weight or Power of Item * Quantity

If an item has an assembly structure, the weight or power of only the parent item is considered for roll-up. Weight and power values come from Mass and Power Consumption attributes of Agile PLM respectively.

No units of measure are assigned to Agile PLM attribute values in Innovation Management.

Assembly

Aggregate of Total Weight or Total Power of each child element

Manually-entered weight or power value at the assembly level will be replaced by the calculated weight or power value after roll-up

Embedded Concept

Rolled-up Weight or Power of the Concept * Quantity

You must roll-up the embedded concept before other roll-ups, otherwise the weight or power calculations will be zero.

Concept

Aggregate of total weight or power of each assembly or element within the root-node

Element refers to a Component, Item or Embedded Concept

Item Score Roll-Up

An Item is said to have complete data if it has values in the following attributes: Overall Compliance, Lead Time and Number of Manufacturer Parts. The following table describes Item Score Roll-Up.

Item score = Points for Overall Compliance + Points for Lead Time + Points for Number of Manufacturer Parts

Attributes

Attribute Values

Score (%)

Equivalent Points

Compliance

Compliant

30%

30

Compliance

Not Compliant or Blank

NA

0

Lead Time

Less than 6

40%

40

Lead Time

Less than 11

NA

30

Lead Time

Less than 21

NA

20

Lead Time

Less than 31

NA

10

Lead Time

More than 30

NA

0

Number of Manufacturer Parts

2 or more

30%

30

Number of Manufacturer Parts

Less than 2

NA

0

Concept Score Roll-Up

The score of a concept or assembly is an aggregation of three item-based score calculations.

Score of a Concept or Assembly Component = A1+A2+A3

  • A1 is the % of items in the concept structure at a lower level than the concept or assembly component

    Number of items/Number of elements in the concept or assembly
  • A2 is the number of items with score >= 85

    Items with score >=85/Total number of items in the concept or assembly
  • A3 is the number of items with complete data

    Items with complete data/Total number of items in the concept or assembly
Note: Embedded concepts are treated as components during concept score roll-ups.

The following table describes concept score roll-ups.

Score Name

Value

Score

Equivalent Points

A1

% of items >= 90%

100%

20

A1

% of items = 80-89%

80%

16

A1

% of items = 70-79%

70%

14

A1

% of items <70%

10%

10

A1

% of items = 0

NA

0

A2

% of items with score =>85 >=90%

100%

60

A2

% of items with score =>85 = 80-89%

80%

48

A2

% of items with score =>85 = 70-79%

70%

42

A2

% of items with score =>85 <70%

50%

30

A2

% of items with score =>85 = 0

NA

0

A3

% of items with complete data = 100%

100%

20

A3

% of items with complete data = 95-99%

80%

16

A3

% of items with complete data = 90-94%

70%

14

A3

% of items with complete data >90%

0

0