How You Print Components List

The Print Components List feature provides you the ability to generate and print the components list for the work order. It provides you the flexibility to view, save and print the report.

As a production supervisor, you can print the components list during the production process when reviewing and managing the work orders.

As part of the components list report, details such as subinventory, locator, operation sequence, name, work center, required quantity, Unit of Measure (UOM), basis, supply type, required date, and substituted are printed. In addition, details of the work order such as work order number, description, product, status, start and completion dates, quantity, project number, task number, and UOM are displayed.

In addition, details of the work order such as work order number, description, product, status, start and completion dates, quantity, and UOM are displayed.

The components list report is printed in the following ways:

  • Select the required work order in the Manage Work Orders page and select the Print Components List action in the Print to PDF Table menu.

  • Select the Print Components List to generate report in .pdf format.

  • To Print Components List scheduled process, select multiple work orders using parameters, such as work order number, dates, product, work center, status, and component required dates.

  • The list of components shown in the report can be grouped by work order and work center, sorted by subinventory and components.

After the successful completion of the scheduled process, the report is generated in .pdf format.

The scheduled process is launched for the selected work orders. The parameters for the scheduled process are:

  • **From Work Order

  • **To Work Order

  • **From Work Order Start Date

  • **To Work Order Start Date

  • **Work Order Product

  • **Item Category

  • Work Center

  • Work Order Status: Default is blank. The other statuses are Unreleased, Released, On Hold, Canceled, Completed, and Closed. In addition, the user-defined statuses of the work order are displayed.

  • From Component Required Date

  • To Component Required Date

  • Project Number (if the organization is tracked by project)

  • Task Number (if the organization is tracked by project)

  • Group By: Values are Work Order and WorkOrder/Work Center

  • Sort By: Values are Subinventory and Component

At least one of the fields marked ** must be entered.

Note: You have an option to enter Submission Notes before you submit the components list for printing.
Note: The .pdf format is available for you to print the document on a local printer.